Campus Project Updates
Please Note: Project schedules are subject to change.
Facilities – Paving Road Work Construction Schedule
Start: Monday, June 14, 2021 – Finish: July 30, 2021 Facilities is paving both the Haverhill and Lawrence Campuses.
Monday, June 14, 2021 – Friday, June 18, 2021 Mobilize onto the site and set up; Demolition in areas where we will be installing drainage and concrete walks.
Monday, June 21, 2021 – Friday, June 25, 2021 Drainage; Demolition of curb.
Monday, June 28, 2021 – Friday, July 2, 2021 Demolition of curb; Construct concrete walks; Reclaim parking lots and roadways; Binder course installation.
Monday, July 6, 2021 – Friday, July 9, 2021 Construct concrete walks; Curb installation.
Monday, July 12, 2021 – Friday, July 16, 2021 Curb installation; Loam edges; Various other tasks.
Monday, July 19, 2021 – Friday, July 23, 2021 Form and pour concrete walks; Tree planting; Sign installation; Cold planing.
Monday, July 26, 2021 – Friday, July 30, 2021 Top course installation, Line painting; Clean up and demobilize.
Facilities – AC Units being replaced in B building & E building
June 2021 Facilities is replacing and installing 77 AC units in both B-building and E-building on campus. Most of this work will be done during weekends and nights when no one is on the area.